Cottage Grove's next Panera Bread is going up on a 0.2-acre former gas station lot at the corner of East Point Douglas Road South, just west of the 80th Street and Highway 61 interchange. That's the stretch the city spent 2026 tearing up and rebuilding.
The roadwork and the new businesses were planned on separate tracks. They're finishing within weeks of each other on the same few blocks, so the corridor that was cones and crossovers in July is where much of the city's newest commercial activity is opening this winter.
The Cottage Grove Journal reported in October that the rehabilitation project was estimated at $16.515 million. It covers 80th Street South between Highway 61 and Ideal Avenue South, plus about 1,000 feet of East Point Douglas Road south of 80th. City, county, MnDOT and federal funds paid for it, along with special assessments. Washington County and MnDOT signed a cost-share agreement with the city for the interchange work, because County Road 39 forms the west leg of the southbound Highway 61 ramp intersection.
Construction started April 27. For drivers who went through it all season, here's what's new:
Mayor Myron Bailey summed up the trade-off in a social media post that the Cottage Grove Journal quoted on Nov. 1:
"Thank you for dealing with the long construction on 80th and the ramps on and off of highway 61. The benefit is new extended turn lanes, added turn lanes, new stop lights with state-of-the art technology to measure and help with traffic flow, a new smooth surface, new street lights, and some new decorate landscaping and signage. You will see the new Holiday decorations on the new street light poles later this November!"
The city scheduled its official ribbon-cutting for Tuesday, Nov. 10, at 9 a.m. The holiday decorations on the new light poles are set to go up later this month.
Property along the corridor helped pay for the work. The City Council approved assessments on 37 parcels belonging to 29 owners. Amounts ranged from $1,900 to $251,500 per parcel and covered residential, commercial and school district properties around 80th Street South and East Point Douglas Road.
The dual left-turn lanes are the biggest change to how traffic moves through the corridor, and they sit where 80th Street meets East Point Douglas Road and Hardwood Avenue. The corridor's new and coming businesses are within a short drive of that intersection.
| Address | Business | Where it stands |
|---|---|---|
| 7420 80th St. S., Suite 203 | Club Pilates | Ribbon-cutting held Oct. 21; upper level of the buildings that house Casa Mia and Great Clips |
| 7162 East Point Douglas Rd. S. | Panera Bread | Former Speedway lot; moving toward completion, and the hoped-for pre-Christmas opening may slip |
| 8621 East Point Douglas Rd. | Wingstop, plus a second restaurant | Former Orange Theory Fitness building, split between two restaurants; the second hasn't been named and no Wingstop opening date is set |
The Panera site has a long history as a fuel station. City planner Max Erickson told the Planning Commission in March that the station was approved in 1981, that the canopy, pumps and signage had already been removed, and that a report on removing the fuel tanks was under review by the Minnesota Pollution Control Agency. The approved plan replaces the old building with a Panera drive-thru with outdoor seating and a rebuilt parking lot. It also closes one of the two southern driveways, so the corner will have fewer curb cuts once the restaurant opens.
At the former Orange Theory building, Bailey said the property owners are working with the neighboring Wendy's to improve landscaping and visibility between the two restaurant sites.
The Journal called Club Pilates part of the "continued commercial activity along the 80th Street corridor." In practice, the Pilates studio opened upstairs from a restaurant and a salon on a road that was still under construction at the time.
The ribbon-cutting doesn't mean the project is fully finished. At the Oct. 7 council meeting, the city's project presenter, Sponholz, said substantial completion was expected by mid-November, with punch-list work to follow and final completion anticipated in June 2027.
The Nov. 6 update on the city's 80th Street project page said lane closures would stay in place on 80th Street and East Point Douglas Road to finish signal, lighting, pavement marking and signing work. At least one lane in every direction was to stay open. Here's what was scheduled for the week of Nov. 9:
Drivers headed to Hastings will notice the ramps most. The southern Highway 61 ramps to and from Hastings stayed closed through late October. The project team's Oct. 30 bulletin expected them to reopen by the end of the week of Nov. 2. The Nov. 6 update set the end of that Friday as the target. The project page has the latest lane and ramp status. The project hotline is (651) 447-7312, and the team takes email at [email protected].
The signal work at Hardwood, Hinton and Grove Plaza affects the same intersections drivers will use to reach the new restaurants. Expect short lane closures there until that work wraps up.
Bailey's same update also listed businesses in other parts of town, on a later timeline.
Kwik Trip, Jamaica Avenue at 95th Street. Bailey said construction has gone smoothly, and a ribbon-cutting is tentatively planned for Dec. 23. This year's mill and overlay work on 95th Street was one of the city's other road projects.
The Basic Needs food pantry site. Bailey said the pantry will move in the next few months to a spot beside Basic Needs near its thrift store off Hadley Avenue. The current pantry property is expected to become a restaurant, and Bailey described it as a non-branded restaurant rather than a national chain. Construction isn't expected to start before January 2027.
Rolling Chapters, 7404 Lamar Ave. S. A new bookstore is getting ready to move into the empty building in Old Cottage Grove next to Boondocks Vintage Boutique.
The city's other big road projects this year were the Highway 19/Keats Avenue and 80th Street roundabout and the 65th Street reconstruction near Hastings Avenue.
On the corridor itself, the projects line up in order. Club Pilates has already opened. Panera's corner is close to finished. Wingstop and its unnamed neighbor don't have opening dates yet, and punch-list work on the road continues toward final completion, anticipated in June 2027.